Steelfixing introduction
Overview
Duration
1 day of 6 learning hours. If e-learning only, the duration is to be at least 50% of this.
Purpose / Scope
The purpose of this standard is to provide the delegate with the knowledge to support the following:
Scope:
- principles of reinforcing concrete including but not limited to pre-cast, post-tension
- storing different types and quality of steel
- methods used to determine cover for rebar
- read and decipher information from rebar drawings and schedules covering 3D formats generated from design software
- methods of tying and when different ties are used
- risk awareness and hazard recognition and mitigation
- deciding between pre-fabrication and in situ steelfixing
- how to read steelfixing drawings and schedules
- how to prefabricate a small ground beam from a drawing and schedule
- pre-pour, placement and post-placement inspections.
Occupational relevance
Training delivered against this standard would be relevant to the following occupational group(s):
- operative and craft
- supervision
- management and leadership.
Delegates pre-requisites
There are no delegate pre-requisites as part of this standard.
Instruction / supervision
As a minimum, course trainers must be able to demonstrate that, in relation to this standard, they have:
- an award in education and training (or equivalent, as per requirements for approved training organisations)
- successfully completed training to this standard
- at least 2 years relevant industrial experience
- a verifiable CV.
Delivery
Delivery may be in an on or off the job environment.
The training requires a flat area of grass or concrete of minimum 12 -15 square metres.
All materials and equipment must be of a suitable quality and quantity for delegates to achieve learning outcomes and must comply with relevant legislation.
The class size and delegate/trainer ratio must allow training to be delivered in a safe manner and enable delegates to achieve the learning outcomes.
The following delivery methods may be used in the delivery of this standard:
- classroom
- a blend of classroom and remote.
This standard is considered to contain 51% or more practical training.
This standard is considered to be set at a basic level.
Assessment
For the successful completion of training, the trainer will be required to make a declaration of the learner’s contribution during the course and that they are confident the learner has understood the content of the course.
Quality assurance
Assured
Quality assurance against this standard will require initial approval of the training organisation and their content mapped to the standard.
CITB will also conduct an approval intervention, either desk-based or centre visit, to ensure the training organisation can meet the requirements of the training standard.
Approved training organisations (ATOs) will be required to present information on records of training and assessment upon request to CITB for desk-based analysis. They will also be visited annually by the CITB quality assurance team.
Renewal
Refresher every 5 years.
Classification
Mandatory Refresher.
Buffer / grace period
3 months.
Approval date
June 2021.
Review cycle
On request or 3 years from approval date.
Learning outcomes
The delegate will be able to:
- outline the principles of using steel to reinforce concrete including but not limited to:
- pre-cast
- post-tension
- list the different types and quality of steel used and implications for storage
- list methods used to determine cover for rebar including the implications of rust
- read and decipher information from rebar drawings and schedules (including side notes) such as cover, splice length, revisions, drawing numbers and 3D formats generated from design software
- use different methods of tying and describe when different ties should be used
- describe the risks involved in steel fixing and how to reduce them
- describe how to recognise the hazards involved in steel fixing and how to mitigate them
- explain how to determine between pre-fabrication or in situ steelfixing
- describe any problems with the steel to the site agent or designer
- prefabricate a small ground beam from a drawing and schedule
- describe how to undertake pre-pour, placement and post-placement inspections Additional information about this standard
Additional information about this standard
The Concrete Society
http://www.concrete.org.uk/
How did we do today? Give feedback